Logo
Help Center
Top
How can we help?
Sign in
  • Getting Started
  • Purchasing Questions
  • Usage Guides
  1. Core Help Center
  2. FAQs
  3. Lists
  • How do I make activity items inactive in bulk?
  • Is there a character limit for activity descriptions?
  • How can I change revenue account associated with activities?
  • How do I create custom payment terms in Core?
  • Can I have different cost rates for same activity?
  • Can I override 'memo is required for time entry' rule for specific activities?
  • Where do I change the default accounts for activity and expense items?
  • Can I create a task to be used for only one project?
  • Can we rename custom fields in Core?
  • Can we have predefined memos for expense items?
Avatar
Core Community-Admin
January 22, 2021 07:40

How do I make activity items inactive in bulk?

You can do that by using the Batch Update feature in the Activity Items screen. Just select the activity items that you want to make inactive and click Actions > Batch Update. In the Batch Update dialog, select the Status field, set its value to Inactive and then click Update. Check the Core Help for more on batch updating activity items.

Was this article helpful?
0 out of 0 found this helpful

Related articles

  • How to I change inactive tasks to active?
  • What are ePayments?
  • Where do I change the default accounts for activity and expense items?
  • Reimbursable flag in Expense Items

© Core Help Center